Next Steps
The timeline below sets out the anticipated schedule for the proposed development.
Thursday 24th
September 2026
Close of public consultation
*All comments received by Thursday 24th September will be considered as part of the planning application preparation process.
September 2026
Project team to review responses received to the public engagement process, and consider necessary amendments to the proposals prior to submission of the planning application
October 2026
Anticipated submission of an outline planning application to Newark and Sherwood District Council*
*Once the planning application has been received and validated by the District Council there will be further opportunity to make comments direct to the Council as part of the planning application process.
Winter 2026
Anticipated determination of the outline planning application by Newark and Sherwood District Council
Winter 2027
Commencement
on site
2032 onwards
Anticipated completion
of development
Harworth would like to hear people’s views on the proposed amendments to the scheme. Comments received as part of this consultation will be carefully considered and used to help shape the proposals prior to the resubmission of the scheme.
Please let us have your comments by Thursday 24th September 2026. Details of how to submit feedback can be found on the Share Your Thoughts page.