Next Steps

The timeline below sets out the anticipated schedule for the proposed development.

Thursday 24th
September 2026

Close of public consultation

*All comments received by Thursday 24th September will be considered as part of the planning application preparation process.


September 2026

Project team to review responses received to the public engagement process, and consider necessary amendments to the proposals prior to submission of the planning application


October 2026

Anticipated submission of an outline planning application to Newark and Sherwood District Council*

*Once the planning application has been received and validated by the District Council there will be further opportunity to make comments direct to the Council as part of the planning application process.


Winter 2026

Anticipated determination of the outline planning application by Newark and Sherwood District Council


Winter 2027

Commencement
on site


2032 onwards

Anticipated completion
of development


Harworth would like to hear people’s views on the proposed amendments to the scheme. Comments received as part of this consultation will be carefully considered and used to help shape the proposals prior to the resubmission of the scheme.

Please let us have your comments by Thursday 24th September 2026. Details of how to submit feedback can be found on the Share Your Thoughts page.